For our Microsoft Office 2007 users...
Multiple Level Undo, Change
Highlighting, and Task Drivers
In Microsoft Office Project Professional 2007, project
managers can visualize the impact of changes and trace back their
steps. To turn the Change Highlighting feature on or off, click the View menu, and
then click Hide
Change Highlighting or Show Change Highlighting. While
the feature is enabled, all levels of tasks affected as a result of a
change are highlighted with a color as a visual indicator.
Using this feature together with the Multiple Level Undo
feature, project managers can do "what-if analysis" by trying
a set of changes and then reversing unwanted changes. If further
analysis of a task's schedule is needed, the project manager can use Task Drivers
on the Project
menu to determine the factors (such as task dependency, calendar
constraints, schedule date, or vacation time) that are driving a task's
start date.
|
|
Register for both
Level 1 and Level 2 Microsoft Project classes and receive a $100.00
discount off the combined registration fee.
|
Contact Full
Circle's instructors by email or by phone at 610-594-9510 if you'd
like us to address a specific software challenge in future Trainer Tip
issues or if you'd like to share your own "tip" with the Full
Circle team. We look forward to hearing from you.
|